The repair of the fixed bed adsorption column, a product of arm field technical company was carried out for the purpose of bringing the faulty equipment back to its normal operating system.
Before this exercise, the equipment was out of operation because of the completely blocked base of the fixed bed column (water column) and the malfunctioning of the air control value.
The sintered bronze plate which formed the base of the water column was cleaned up and freed from debris which originally blocked the porosity of the plate to an unacceptably level. To do this, the plate was soaked in a diluted acetic acid and a current of air used to free the tiny openings from blockage. Later, the air control valve where properly reactivated, rectified and recalibrated.
At the end the operation of the equipment came back to normal functioning. The entire equipment was cleaned up and lubricated.
The fluidized bed was run and found to be in good order.
Title page
Letter of transmittal
Acknowledgement
Dedication
Abstract
Table of content
1.0 CHAPTER ONE –
INTRODUCTION
2.0 CHAPTER TWO –
LITERATURE REVIEW
2.1 Absorption
2.2 Types of Absorption
2.2.1 Physical Absorption
2.2.2 Chemical Absorption
2.3 Absorbents
2.4 Desorption
2.4.1 Desorption Methods
2.5 Desorption Operation
2.5.1 Stagewise Operation
2.5.2 Continuous Contact
2.6 Analysis of Fixed – Bed Adsorption
2.7 Adsorption of Solute from Dilute Solution
2.8 The Process of Welding
2.8.1 Oxy-Acetylene Welding
CHAPTER THREE
3.0 REFURBISHING PROCEDURE
CHAPTER FOUR
4.0 OPERATION OF THE EQUIPMENT
CHAPTER FIVE
Conclusion
CHAPTER SIX
6.0 Recommendation
Refurbishing Of A Fixed And Fluidized Bed. (n.d.). UniTopics. https://www.unitopics.com/project/material/refurbishing-of-a-fixed-and-fluidized-bed/
“Refurbishing Of A Fixed And Fluidized Bed.” UniTopics, https://www.unitopics.com/project/material/refurbishing-of-a-fixed-and-fluidized-bed/. Accessed 22 November 2024.
“Refurbishing Of A Fixed And Fluidized Bed.” UniTopics, Accessed November 22, 2024. https://www.unitopics.com/project/material/refurbishing-of-a-fixed-and-fluidized-bed/
Here’s a typical structure for Refurbishing Of A Fixed And Fluidized Bed research projects:
- The title page of Refurbishing Of A Fixed And Fluidized Bed should include the project title, your name, institution, and date.
- The abstract of Refurbishing Of A Fixed And Fluidized Bed should be a summary of around 150-250 words and should highlight the main objectives, methods, results, and conclusions.
- The introduction of Refurbishing Of A Fixed And Fluidized Bed should provide the background information, outline the research problem, and state the objectives and significance of the study.
- Review existing research related to Refurbishing Of A Fixed And Fluidized Bed, identifying gaps the study aims to fill.
- The methodology section of Refurbishing Of A Fixed And Fluidized Bed should describe the research design, data collection methods, and analytical techniques used.
- Present the findings of the Refurbishing Of A Fixed And Fluidized Bed research study using tables, charts, and graphs to illustrate key points.
- Interpret Refurbishing Of A Fixed And Fluidized Bed results, discussing their implications, limitations, and potential areas for future research.
- Summarize the main findings of the Refurbishing Of A Fixed And Fluidized Bed study and restate its significance.
- List all the sources you cited in Refurbishing Of A Fixed And Fluidized Bed project, following a specific citation style (e.g., APA, MLA, Chicago).